What was promised What got built

Battery Park Community Activism is an independent, resident-run ledger of the flood-wall construction remaking Battery Park City and The Battery: every budget, date and closure held against what was delivered.

See the projects

The estimates grew

$1.19B

Growth between each project's first public estimate and its current one, across the 5 projects old enough to have both, as of Oct 2026.

It would build the Battery Playscape, this program's on-budget playground, 64 more times. Every figure is sourced on its project page.

Drawn, then built

In 2022 the BPCA showed Community Board 1 a sunlit lawn full of people; in the week Wagner Park reopened in part, nearly three years later, its pavilion stood behind barriers.

Rendering of a sunlit Wagner Park lawn under full-grown shade trees, a child cartwheeling and people picnicking and strolling across the grass
The lawn as the BPCA presented it to Community Board 1 on September 20, 2022: a rendering from the agency's own deck.
The rebuilt Wagner Park lawn under a grey sky, the new rust-red arched pavilion behind orange and white barriers and a Pardon Our Appearance sign, the Museum of Jewish Heritage at left and One World Trade Center beyond
Wagner Park on August 1, 2025, three days after it reopened in part.

Five projects, one ledger

First public cost estimate for each project next to the latest one. Estimates change for real reasons, including scope changes and inflation. The sources behind every figure are on each project page.

$2.23B

Current estimated cost of the 5 projects tracked here, nearly all of it public money

+114%

Cost growth on the 5 projects old enough to have both a first and a current estimate

10 years

Combined schedule slip so far, measured against the completion dates announced at launch

Each project by the year it was announced: its first public cost estimate against its current one, and how far it runs behind the completion date promised at announcement
2019 The Battery Coastal Resilience $165M to $200M +2.5 yrs behind schedule
2019 BPC Ball Fields Interim Flood Barriers $4.5M to $7M +1 yr behind schedule
2020 Battery Playscape $18M to $18M +1 yr behind schedule
2021 South Battery Park City Resiliency $221M to $303M +2 yrs behind schedule
2021 North/West Battery Park City Resiliency $631M to $1.7B +3.5 yrs behind schedule
First public estimateCurrent estimateSouth BPCSouth BPC · first public estimate: $221M$221MSouth BPC · current estimate: $303M, +$82M, +37% over the first public estimate$303M+$82M, +37%North/West BPCNorth/West BPC · first public estimate: $631M$631MNorth/West BPC · current estimate: $1.7B, +$1.07B, +169% over the first public estimate$1.7B+$1.07B, +169%The Battery wharfThe Battery wharf · first public estimate: $165M$165MThe Battery wharf · current estimate: $200M, +$35M, +21% over the first public estimate$200M+$35M, +21%Ball fieldsBall fields · first public estimate: $4.5M$4.5MBall fields · current estimate: $7M, +$2.5M, +56% over the first public estimate$7M+$2.5M, +56%PlayscapePlayscape · first public estimate: $18M$18MPlayscape · current estimate: $18M, on budget$18Mon budgetFirst public estimateCurrent estimateSouth BPCSouth BPC · first public estimate: $221M$221MSouth BPC · current estimate: $303M, +$82M, +37% over the first public estimate$303M+$82M, +37%North/West BPCNorth/West BPC · first public estimate: $631M$631MNorth/West BPC · current estimate: $1.7B, +$1.07B, +169% over the first public estimate$1.7B+$1.07B, +169%The Battery wharfThe Battery wharf · first public estimate: $165M$165MThe Battery wharf · current estimate: $200M, +$35M, +21% over the first public estimate$200M+$35M, +21%Ball fieldsBall fields · first public estimate: $4.5M$4.5MBall fields · current estimate: $7M, +$2.5M, +56% over the first public estimate$7M+$2.5M, +56%PlayscapePlayscape · first public estimate: $18M$18MPlayscape · current estimate: $18M, on budget$18Mon budgetFirst public estimateCurrent estimateSouth BPCSouth BPC · first public estimate: $221M$221MSouth BPC · current estimate: $303M, +$82M, +37% over the first public estimate$303M+$82M, +37%North/West BPCNorth/West BPC · first public estimate: $631M$631MNorth/West BPC · current estimate: $1.7B, +$1.07B, +169% over the first public estimate$1.7B+$1.07B, +169%The Battery wharfThe Battery wharf · first public estimate: $165M$165MThe Battery wharf · current estimate: $200M, +$35M, +21% over the first public estimate$200M+$35M, +21%Ball fieldsBall fields · first public estimate: $4.5M$4.5MBall fields · current estimate: $7M, +$2.5M, +56% over the first public estimate$7M+$2.5M, +56%PlayscapePlayscape · first public estimate: $18M$18MPlayscape · current estimate: $18M, on budget$18Mon budget

Figures as of Oct 2026. Hover any bar for the exact figure, or open a project for the full budget history and sources. Click a bar to open that project.

The schedule, by project

Each project's announced construction window against its current one; the red is the slip.

Announced windowCurrent windowSlip202020222024202620282030todaySouth BPCSouth BPC · announced: 2022 to 2024South BPC · actual: Sep 2022 to Sep 24, 2026South BPC · slip: 2024 to Sep 24, 2026, +2 yrs+2 yrsNorth/West BPCNorth/West BPC · announced: Jul 2023 to 2027North/West BPC · current estimate: Nov 2025 to Dec 2030North/West BPC · slip: 2027 to Dec 2030, +3.5 yrs+3.5 yrsThe Battery wharfThe Battery wharf · announced: Oct 2022 to Dec 2024The Battery wharf · current estimate: Jan 2024 to Jun 2027The Battery wharf · slip: Dec 2024 to Jun 2027, +2.5 yrs+2.5 yrsBall fieldsBall fields · announced: Feb 2020 to Aug 2020Ball fields · actual: May 2021 to Oct 2021Ball fields · slip: Aug 2020 to Oct 2021, +1 yr+1 yrPlayscapePlayscape · announced: Dec 2019 to Mar 2021Playscape · actual: Dec 2019 to Dec 16, 2021Playscape · slip: Mar 2021 to Dec 16, 2021, +1 yr+1 yrAnnounced windowCurrent windowSlip202020222024202620282030todaySouth BPCSouth BPC · announced: 2022 to 2024South BPC · actual: Sep 2022 to Sep 24, 2026South BPC · slip: 2024 to Sep 24, 2026, +2 yrs+2 yrsNorth/West BPCNorth/West BPC · announced: Jul 2023 to 2027North/West BPC · current estimate: Nov 2025 to Dec 2030North/West BPC · slip: 2027 to Dec 2030, +3.5 yrs+3.5 yrsThe Battery wharfThe Battery wharf · announced: Oct 2022 to Dec 2024The Battery wharf · current estimate: Jan 2024 to Jun 2027The Battery wharf · slip: Dec 2024 to Jun 2027, +2.5 yrs+2.5 yrsBall fieldsBall fields · announced: Feb 2020 to Aug 2020Ball fields · actual: May 2021 to Oct 2021Ball fields · slip: Aug 2020 to Oct 2021, +1 yr+1 yrPlayscapePlayscape · announced: Dec 2019 to Mar 2021Playscape · actual: Dec 2019 to Dec 16, 2021Playscape · slip: Mar 2021 to Dec 16, 2021, +1 yr+1 yrAnnounced windowCurrent windowSlip202020252030todaySouth BPCSouth BPC · announced: 2022 to 2024South BPC · actual: Sep 2022 to Sep 24, 2026South BPC · slip: 2024 to Sep 24, 2026, +2 yrs+2 yrsNorth/West BPCNorth/West BPC · announced: Jul 2023 to 2027North/West BPC · current estimate: Nov 2025 to Dec 2030North/West BPC · slip: 2027 to Dec 2030, +3.5 yrs+3.5 yrsThe Battery wharfThe Battery wharf · announced: Oct 2022 to Dec 2024The Battery wharf · current estimate: Jan 2024 to Jun 2027The Battery wharf · slip: Dec 2024 to Jun 2027, +2.5 yrs+2.5 yrsBall fieldsBall fields · announced: Feb 2020 to Aug 2020Ball fields · actual: May 2021 to Oct 2021Ball fields · slip: Aug 2020 to Oct 2021, +1 yr+1 yrPlayscapePlayscape · announced: Dec 2019 to Mar 2021Playscape · actual: Dec 2019 to Dec 16, 2021Playscape · slip: Mar 2021 to Dec 16, 2021, +1 yr+1 yr

Who pays

Battery Park City's projects are not paid for out of the city or state budget. The BPCA borrows against money its residents and businesses already pay, and as the estimates grew, so did its borrowing cap.

The entrance to the Battery Park Underpass filled with harbor water to just below its clearance sign, street lamps standing in the flood, the morning after Hurricane Sandy
The Battery Park Underpass on October 30, 2012. This is the flood the projects answer.

Who pays. The BPCA borrows against the ground rent and payments in lieu of taxes that Battery Park City's residents and businesses already pay, money that would otherwise flow to the city's general fund. As costs grew, Albany raised the authority's borrowing cap from $500M to $1.5B in 2023, then to $2.5B in 2024, and the BPCA sold $658M in bonds in December 2025 with more issuances planned annually until the North/West project is done. The Battery's wharf is different: it is city capital money through NYCEDC and NYC Parks.

What it buys. Mostly buried flood protection: Wagner Park rebuilt roughly ten feet higher over a buried floodwall, flip-up gates at Pier A Plaza, The Battery's wharf raised about five feet, and about 1.5 miles of North/West floodwalls, tide gates and a deployable West Street crossing. The BPCA's own benefit-cost analysis argues the program is worth it, projecting $3.5B in benefits against $1.6B in present-value costs. That case gets stronger or weaker with every overrun, which is why this ledger exists.

Where. From high ground in Tribeca down the Esplanade and West Street to South Cove, then through Wagner Park and Pier A Plaza to The Battery's waterfront: one stretch of a roughly 3.5-mile protective alignment around Lower Manhattan.

What you can do. The BPCA board, Community Board 1 and the construction committee all take public comment, and written comments and records requests create a paper trail that officials must answer to. Where and when to show up.

The projects

Each project with its status, its current estimate, and its growth since the first public estimate
South Battery Park City Resiliency Declared complete by the BPCA, September 24, 2026 $303M +37% over the first estimate
North/West Battery Park City Resiliency Early construction, to late 2030 $1.7B +169% over the first estimate
The Battery Coastal Resilience Phase 1 open, Phase 2 to 2027 $200M +21% over the first estimate
BPC Ball Fields Interim Flood Barriers Complete, interim protection $7M +56% over the first estimate
Battery Playscape Complete, opened 2021 $18M on budget

The landfill, June 1974

Aerial photograph of the bare Battery Park City landfill in June 1974, a flat expanse of sand and construction vehicles beside the Hudson piers, with the elevated West Side Highway and the new Twin Towers behind
The landfill that became Battery Park City, June 1974. The neighborhood the BPCA's flood walls now protect was built on it.

The biggest jump

North/West's public estimate grew from $631M in 2021 to $1.7B in Nov 2025, up 169%, before major construction began. Every step in between was a public statement: $1B in Jun 2023, $1.5B in Jun 2024, $1.6B in Oct 2025. The full history and its sources are on the project page.

First public estimate, 2021

$631M

Current estimate, Nov 2025

$1.7B

At Albany Street

The North/West project at Albany Street: the Upper Room two days after its demolition, and the esplanade gated six months later.

A yellow excavator in a field of broken concrete where the Upper Room stood at Albany Street, construction fencing and a contractor's truck beside it, apartment buildings behind
The Upper Room, November 14, 2025.
Two chain-link gates closing the esplanade at Albany Street, hung with detour and esplanade-closed signs, orange water barriers at their feet and green-screened construction fence behind
Albany Street, May 2026.

Beyond the ledger

All impacts

The BPCA board, Community Board 1 and the construction committee all take public comment. Here is where and when. Attend