South Battery Park City Resiliency
A continuous line of flood protection from the Museum of Jewish Heritage through Wagner Park and Pier A Plaza to the northern edge of The Battery. Wagner Park was demolished and rebuilt roughly ten feet higher over a buried floodwall, with flip-up gates at Pier A Plaza rated for the 100-year storm.
Wagner Park, then and now
The park the project demolished, and the park it rebuilt over a buried floodwall, in its first week back.


The budget over time
Each point is a public statement of the project's estimated cost, from the agency or from official documents and press coverage of them.
View this data as a table
| Date | Estimate | Context | Source |
|---|---|---|---|
| 2021 | $221,000,000 | Budget as announced in 2021-22; the city's LMCR page still showed this figure in October 2026 | nyc.gov |
| Dec 2024 | $296,000,000 | Widely reported from late 2024, and the figure at Wagner Park's reopening | newyorkyimby.com |
| Jun 2026 | $302,772,000 | BPCA board update: $296.1M budget plus a reported $6.7M overage, including proposed settlements and acceleration costs | media.bpca.ny.gov |
The schedule
The construction window announced when the project was unveiled, against what actually happened. Below the bars, the features the project promised, each with the date promised at announcement and the date it actually arrived, if it has.
Promised versus delivered

What was promised
- A two-year construction period starting summer 2022, with the park back in service in 2024
- Access closed to Pier A Plaza and portions of The Battery along Battery Place for about 20 months, per the July 2022 construction staging presentation to CB1
- Construction planned around a single 7 AM to 3 PM weekday shift, occasionally extended to 6 PM for critical tasks, with weekend or night work only occasionally required, per the FEIS
- Total cost of $221M, funded by BPCA bond proceeds
- Wagner Park rebuilt with expansive lawns and gardens, public restrooms, dining, and access for all
- After community pressure, an August 2022 redesign promised 74 percent more green space than the first redesign proposal
- A new pavilion with a restaurant, classroom, public restrooms, and a publicly accessible rooftop
- Flood protection that removes the area from the FEMA flood zone

What happened
- changedWagner Park reopened July 29, 2025, about a year past the original 2024 promise. The BPCA notice that closed the park on November 16, 2022 said the work would take roughly two years; the reopening came two years and eight months later
- changedPier A Plaza and the north edge of The Battery were fenced on October 16, 2023 for work the BPCA said would continue through summer 2025. Lower Pier A Plaza reopened with connections to Wagner Park and Battery Park by June 12, 2026, about 32 months after fencing and a year past that estimate, with Battery Place work continuing through at least September 11, 2026, the end of the BPCA's last two-week notification, before the BPCA declared the project complete on September 24, 2026
- changedWork hours grew far past the FEIS's single-shift assumption: regular Saturday work from December 2024, notification headers reading 7 AM to 6 PM including weekends from August 2025, double shifts to 11 PM from February 2026, Sunday hours from spring 2026, and overnight 9 PM to 5 AM stretches in spring 2025 and June 2026. The last notification to state the 11 PM shift covered June 26 to July 10, 2026; the four that followed, the last covering through September 11, list 7 AM to 6 PM including weekends
- changedCost rose from $221M to $296.1M, and the BPCA's June 2026 board update added a $6.7M overage, bringing the anticipated total to about $302.8M, 37 percent over the announced figure. The BPCA had published no final cost when it declared the project complete in September 2026: its completion release states no cost, and its last budget statement remains the June 3 update
- changedThe rebuilt lawns hold roughly 10 percent less green space than the pre-demolition park, and its 139 new trees are 48 fewer than the old park had
- changedThe pavilion opened in phases, none of it ready at the July 2025 reopening: restrooms fall 2025, the rooftop with its observation deck on November 10, 2025, the classroom in early 2026
- changedThe restaurant had not been announced as open as of October 2026. The first operator RFP drew zero responses; a relaunched RFP produced an operator, reported in June 2025 and named by the BPCA that September as Jabber Dorado Enterprises, with fit-out estimated at six to nine months from November 2025 and an opening in summer 2026. The BPCA repeated summer 2026 at the November 2025 rooftop unveiling and on March 24, 2026; its March 4 board update scheduled turnover of the space for mid March, and its June 3 update lists the restaurant as turned over, without a date. Summer 2026 passed with no opening announced, and the BPCA's September 24 completion release does not mention the restaurant. Gigino, the restaurant the demolition displaced, served its last meal September 5, 2022
- changedThe viewing platform over the Pier A inlet, which the BPCA's December 2025 board update scheduled for mid December 2025, had been completed and opened to the public by January 28, 2026, according to that day's board minutes, posted in September. Veneer work around the columns limited access to the inlet area into July 2026, and the BPCA's September 24 completion release lists modifications to the inlet at Pier A among the finished components
- keptThe buried floodwall, flip-up gates at Pier A Plaza, tide-gate chamber, and 63,000-gallon stormwater cistern were built
- keptPublic artworks by Tony Cragg and Louise Bourgeois returned to the park
- changedThe Pier A Plaza and Battery segment, which BPCA board updates targeted for late May 2026 (December and March) and then for July 4, 2026 (June 3), was still 85 percent complete on July 27, when the BPCA told Community Board 1 it would be finished in fall 2026. The BPCA declared the project complete on September 24, 2026
- pendingWhether the neighborhood leaves the FEMA flood zone is still open: the BPCA's monthly monitoring reports describe the purpose of the flood alignment as meeting 'the requirements for FEMA accreditation', and no document reviewed for this page says FEMA has accredited the system or changed the flood maps
Friction and open questions
Disputes, community objections, and unresolved issues on the public record.
- Residents fought the demolition of the functioning, celebrated 1996 park, calling it a plan to destroy a green space in order to save it. A neighborhood association lawsuit paused work in December 2022; a court denied the injunction in February 2023 and demolition proceeded.
- Post-reopening criticism has centered on less shade, more hardscape, a smaller lawn, and the loss of the old waterside dining terrace.
- The city's official LMCR page still displayed the stale $221M figure on October 23, 2026, a month after the BPCA declared the project complete, five years and about $80M out of date; amNewYork and 6sqft repeated $221M in their coverage of the completion.
- The BPCA's completion estimates for the final stretch of work read as a moving target: seven consecutive two-week notifications, March 6 through May 29, 2026, each said the double-shift work at Pier A Plaza and Battery Place would continue approximately 10 more weeks. The June 12 notice said approximately 4 more weeks; the June 26 notice said approximately 9 more weeks. No notification after June 26 repeated an estimate: the four that followed, the last covering through September 11, listed work from 7 AM to 6 PM including weekends and said nothing about the extra shift or how many weeks remained. The BPCA declared the project complete on September 24.
- The restaurant has no announced opening date as of October 2026. The BPCA's last dated target was summer 2026, first given in a September 2025 presentation to Community Board 1, repeated on November 10, 2025, and restated on March 24, 2026 ('a restaurant will open in the Pavilion this summer'). Its September 24, 2026 completion release names the rooftop and the classroom as earlier milestones and does not mention the restaurant. An opening in 2027 would put the neighborhood's wait at five years since Gigino closed for the demolition in September 2022.
- The completion came with open money questions. On June 3, 2026 the BPCA board approved a $3.1M increase to the Wagner Park site-work contract 'for the settlement of all impact and delay-related claims', and its September 16 board packet asked the members to add $3.6M to the Pier A Plaza contract, from $81,593,000 to $85,193,000, and to extend its term by 12 months, to October 30, 2027. The September 16 minutes are not yet posted, and the BPCA has not said how these sums relate to the reported $6.7M overage.

Sources
- Official project page
- South Battery Park City Resiliency Project, BPCA official page
- BPCA board update on SBPCR, showing the $6.7M overage
- Plan to destroy then rebuild Wagner Park, THE CITY
- Battery Park City Resilience Projects, city LMCR page with stale figures
- Wagner Park reopens with climate resiliency features, New York YIMBY
- Battery Park City Neighborhood Association v. BPCA, case record
- Wagner Park has reopened, Tribeca Citizen
- The Price of Resiliency, The Broadsheet
- LMCR construction staging update to Manhattan CB1, with announced closure durations
- BPCA community notice closing Wagner Park, work to take roughly two years
- BPCA community notice: Battery and Pier A Plaza fencing, work through summer 2025
- SBPCR Final Environmental Impact Statement, construction chapter, with the work-hour assumptions
- SBPCR two-week construction notification, June 26 to July 10, 2026
- BPCA community notice: regular Saturday work begins
- Gigino at Wagner will not (necessarily) return, Tribeca Citizen, with the September 5, 2022 closing
- Waiting for a Table, The Broadsheet, on the restaurant RFP that drew zero responses
- BPCA unveils Wagner Park pavilion rooftop, with the summer 2026 restaurant target
- What restaurant is coming to the pavilion at Wagner Park, Tribeca Citizen
- BPCA SBPCR board update, March 2026: restaurant turn-over mid March, Pier A segment 75 percent
- BPCA press release PR07-26: completion of the South Battery Park City Resiliency Project and reopening of the Battery Bikeway
- SBPCR two-week construction notification, August 28 to September 11, 2026, the last one posted
- BPCA update to CB1's Battery Park City Committee, July 27, 2026: Pier A and The Battery 85 percent complete, Package 4 completion fall 2026
- BPCA board minutes, January 28, 2026: the Pier A inlet viewing platform completed and open to the public
- BPCA board minutes, June 3, 2026: settlement of the Wagner Park contractor's impact and delay claims
- BPCA board packet, September 16, 2026: proposed $3.6M increase and 12-month extension for the Pier A Plaza contract
- BPCA presentation to CB1 on the Wagner Park Pavilion restaurant, September 2025: operator and estimated timeline
- BPCA release unveiling The Classroom, March 24, 2026: a restaurant will open in the Pavilion this summer
- Oyster Research Station Launched on Battery Park City's New Tide Deck, Tribeca Trib
- Battery Bikeway reopens with completion of $221M flood-resiliency project, 6sqft, repeating the stale figure
- SBPCR monthly community air quality monitoring report, July 2026, with the FEMA accreditation purpose statement